Steve Packer, Senior Planning Officer dealing with P/2012/0573 has announced that the meeting scheduled for 28 April to consider access to the proposed Reeves Hill Wind farm has been cancelled.   This is because Natural Resources Wales are not satisfied with the applicant’s Construction Ecology Management Plan. Prior to this, SHCG produced an extended critique of the CEMP and communicated our misgivings to NRW.  Many of our points are reflected in a report sent to NRW by Powys and in the NRW report then sent to Powys.

Dulas has indicated that they will submit a new CEMP addressing the shortcomings identified by NRW by 24 April.  The revised CEMP will then go out to public consultation and a new Planning Committee Meeting will be scheduled.